After several project delays, the project manager has determined that changes are needed to the product deliverables to ensure quality. The project manager takes the following steps:
What should the project manager do next?
A deliverable on the project’s critical path is behind schedule.
The cost performance index (CPI) is 1.3. The project manager can put the project back on schedule.
Which three results are the most likely for this project?
(Choose three)
During the daily standup meeting a team member suggests that rework is being caused because there seems to be too much work.
How should the project manager respond to this?
During a conversation with a friend, the project manager hears that union action may occur within the next two weeks. The project manager knows that at this stage of the project, any project delays could cause substantial harm to both budget and schedule, and any union action will affect the project team.
Earlier, the probability of a union action was considered minimal, so it was unanticipated. Also, the project manager has worked successfully with the union in the past.
How should the project manager respond to this issue?
Project Alpha is developing a customer service prototype for a company’s marketing department. The customer stakeholder group introduces it to franchise owners and direct customers of the company. The prototype scores 95% of the functional requirements defined in the scope, which results in a passing score based on the project’s agreed upon quality metrics.
The franchise group is unwilling to approve the prototype since it does not fulfill a particular functional requirement, even though the direct customer group approves.
How can the project manager handle communication with this diverse stakeholder group?
Over the past six months, the development cost per story has risen by more than 250% due to a faulty platform that is no longer supported. The product vision highlights the platform’s unique features that are prerequisites for the product.
What should the project manager do to determine next steps?
A project involves six different companies, and the project sponsor is part of a global organization. At the midpoint of the project, the project manager learns that one stakeholder is experiencing difficulties and cannot provide their level of involvement.
The project manager needs to do __________________ and then ___________________.
Fill in the blanks of the correct pairs of answers
After issuing a test summary report with no significant defects, an analyst performs some additional testing where a defect is discovered and you are immediately notified. You are scheduled to meet later today with stakeholders to obtain their acceptance of the final deliverable.
What should the project manager do?
While preparing a project’s third progress report, the project manager identifies that the project will experience delays due to late material deliveries. The two previous project reports indicated that the project was on track.
What should the project manager do next?
A project team implements a change approved by the change control board (CCB). The change was intended to minimize risk but had the opposite effect.
What should the project manager have done to avoid this outcome?
Due to increased price volatility, a vendor asks the project manager of a large development project to make a price change that will affect the project contract.
What should the project manager do?
During user testing, the client agreed to the final product. One day later, the client indicated that it may not be acceptable.
What should be the project manager’s first step for resolving this issue?
During a meeting, a project manager learns that a business result needs to be delivered in four weeks, although the original schedule stated 16 weeks. The project manager also realizes that there is no technical resource available. The project manager knows the technical resource manager because they have worked together on a previous project.
What would be the first thing the project manager should do?
A project that should have been 90% complete by now is only 65% complete. The total budget is $120,000 US, and the actual costs spent to date (AC) is $80,000.
What is the schedule performance index and cost performance index of the project?
An energy infrastructure vendor delivers a complex solution proof of concept to a new strategic customer. The predictive project should be complete in 10 weeks, but there is an extensive list of outstanding items, and some are dependent on external events with uncertain scheduling.
How should the project manager handle this outstanding item?
In a weekly project status meeting, a key team member expresses concerns about the overall approach documented within the project management plan. The project manager is surprised because the team is executing a vital component of the project, and the concern has not been raised before.
What steps should the project manager take?
After missing two consecutive major deadlines because of delayed glass deliveries, a manufacturing company changed the glass supplier to meet production deadlines. Three months later, production reports quality problems with the new glass. The project manager determines that the supplier change caused quality problems.
How should the project manager avoid this issue in the future?
The quarterly results show that the competitors are driving prices down. The company is losing market share midway through a product development project, and the sponsoring unit is not likely to get a return on its investment.
Which two actions should the project manager take to adapt the project to those new conditions?
(Choose two)
Which of the most urgent threat listed in the risk register?
Risk Probability Impact Trigger date
R1 high medium June 30
R2 low low June 14
$3 high high June 21
$5 medium medium June 10
While preparing a project’s third progress report, the project manager identifies that the project will experience delays due to late material deliveries. The two previous project reports indicated that the project was on track.
What should the project manager do next?
A key stakeholder requests a change that will solve a critical issue that might affect the continuity of operations. However, the project is nearing completion, and the change would increase the overall project cost and delay the completion date.
What should the project manager do?
Two key stakeholders, who are also members of the change control board (CCB), complain they were not aware of an extension to the project schedule. The project manager knows that the extension was necessary to add value to the project.
What should the project manager have done to avoid this issue?
Quarterly results show that competitors are driving prices down. The company is losing market share, and midway into the project development project, it appears the sponsoring unit is not likely to get a return on their investment.
Which two actions should the project manager take to adapt the project to these new conditions?
(Choose two)
The project sponsor requests that an element of the product be swapped for equipment supplied by a local manufacturer in order to have a more sustainable supply chain.
Which action should the project manager take?
A project has the following characteristics:
Which step should the project manager take?
The last three agile iterations showed a trend of increasingly prolonged test work.
Which activity about the project which activity should the project manager plan to address the root cause?
A recently formed agile team is exhausted after working 12-hour days to fulfill sprint commitments.
Who needs to properly perform their duties in this situation?
In response to slippage on some scheduled tasks, the project manager re-prioritized the number of subsequent tasks to try fixing the problem.
This did not work, so the project manager needed to escalate the issue.
Which two items does the project manager need to consult?
(Choose two)
A project manager is managing a credit card acceptance software project. During testing, it was learned that the application cannot accept foreign credit cards, making it nearly useless. The team leader had entered a user story that said, “Customer can pay using a credit card,” but it was put into the backlog as too large for the sprint.
What should have been done as a project manager to prevent this issue?
After monitoring a product’s development after the first three releases, the product owner wants to launch a product even though it lacks some features identified in the minimum viable product (MVP). A stakeholder is not satisfied with this version and feels it needs to meet the previously agreed-upon MVP definition.
How should the project manager proceed?
A project that should have been 90 percent complete by now is only 45 percent complete. The total project budget is US$110,000, and the actual cost of work performed is US$60,000.
What can be determined from this information?
A stakeholder learns that the equipment purchased for a project is higher quality than initially agreed upon. The stakeholders are concerned that this deviation has negatively impacted the budget. The stakeholder contacts the project manager and demands clarification.
What action should the project manager have taken to avoid the situation?
In an iteration review, the definition of done (DoD) was not met.
What is an appropriate way for the project manager to proceed?
An agile innovation team is highly productive. However, the head of operations informs the product owner that the company is not getting sustainable return on investment from the team’s work.
How should the product owner address the problem?
In a hybrid product design project, the team encounters a 3D printer malfunction, resulting in costly losses of titanium supplies. When the production team tells the agile programming team about the problem, it becomes clear that mistranslated data sheets create issues for both teams. However, the agile team resolved their problems a month before the malfunction.
What could the agile team have done to prevent the current malfunction?
After three agile iterations, the project showed a trend of increasingly prolonged test work, which the team performed, causing intensive backlog refinement.
What metrics show that the problem was effectively addressed?
While a project manager prepares the monthly project status report, four new risks are identified. These new risks could affect critical milestones.
What should the project manager do before presenting this new risk information?
The project manager learns that one team member needs to complete a critical path activity outside of the project, resulting in a scheduling risk for the project.
What can be done to help the project manager eliminate this risk?
A project that should have been 90% complete by now is only 84% complete. The total budget is $110,000 USD and the actual cost to date is $82,000 USD.
What is this project’s schedule performance index SPI and the cost performance index CPI?
After 20% of the project was completed, the customer decided to change the provider for data center implementation. The new provider’s project manager requested a meeting with the customer to clarify the project’s impact if the requirements were not well gathered.
Which project areas could be impacted if the requirements are not well gathered? (Choose 3)
During the fourth iteration of an agile project, the customer requests a technical change to the development of the project deliverable.
What should the project manager do in this situation?
During a project meeting, a team member informs the project manager that a due task was not completed on time because of a last-minute work crisis.
What should the project manager do?
As a predictive project enters the execution phase, a functional manager discovers that one of the materials to be used in the product will harm the environment and urges the project manager to switch to a more environmentally friendly material. What should the project manager’s initial response be?
A project manager is hired to lead a project with an international pharmaceutical company. The project is in the planning stage and must adhere to a strict budget and timeline to beat competitors to market. While reviewing the project initiation documents, the project manager realizes that cost and schedule estimations for a required regulatory review have not been completed.
Which two actions should the project manager take? (Choose 2)
A local government passes a law that affects the scope of a project currently in the execution phase. The regulation change was unforeseen and will take effect within weeks of the law passing. The project manager knows that the project schedule and budget will be impacted.
What should the project manager do?
The latest software built for a virtual reality headset release did not include urgent change requests already implemented by the electronics work stream. The product owner informed the software team about the change during a daily meeting, but no one recorded it.
What should the project manager do to avoid this problem in the future?
The customer contemplates adding new features to a project deliverable.
Which mandatory step must the project manager take before a project team member can start working on these new features?
Due to resource challenges, a contractor is late with a credit critical project deliverable, even though the work is nearly complete. The project must be delivered on time because the next project depends on the on–time completion of this one.
There is a 22% buffer in the project schedule for cost overruns, but only three weeks left in the schedule.
How can the project manager resolve this issue?
A hybrid project combines IT integration and software development tasks. The predictive and agile teams seem to be working in silos, resulting in misaligned deliverables and scheduling issues.
Which two measures most effectively enable the team to better synchronize their deliverables?
(Choose two)
Company executives closely monitor its progress six months into a strategic agile project. The COO expresses frustration that the last weekly burn-down chart shows the projected completion date significantly late, moving back and forward several times.
How can the project manager forecast the completion date more accurately and with more certainty?
The IT integration team has a significant setback in a hybrid project. Testing has confirmed that the hardware does not support the target operating system. The agile team software release must now run on a later operating system version.
What should the project manager do next?
A sponsor proposes a project scope change that is popular with the project team and key stakeholders.
What should the project manager do?
A team member is working on a critical task for a project and approaches the project manager immediately before the start of a project meeting and informs the project manager that the task was not completed on time.
What should the project manager do?
A project manager is new to the organization and is assigned to replace the project manager of an active project. What should be one of the first things the project manager does?
A manufacturing project is in the implementation phase. During a status meeting, a team member tells the project manager that a solution has been found for a persistent failure of equipment used in the implementation; however, this solution is temporary, and the equipment could fail again.
Which document should the project manager update?
A software development project is using a hybrid development approach to apply the cost and schedule controls mandated by the project sponsor. The project team completed its second iteration 3 days earlier than planned.
Which two actions should the project team take? (Choose 2)
A project team is working on an older server to develop a software application. The team has ordered a new server for end-user testing as the older server cannot perform this testing. The new server has not arrived in time for the scheduled testing window, delaying the end-user testing.
What should the project manager do in this situation?
Over the past six months, the cost per story point in agile projects has risen by more than 250% due to a faulty platform that is no longer supported. The project will exceed the budget increment threshold at the next iteration.
Who should decide whether the project should be canceled?
A customer requests a change in the technical approach for product development. The project manager learns about this request during a recurring project review.
How should the project manager respond?
A client’s employee asks the project manager for an additional, new product feature during a status meeting.
To which document should the project manager first refer to determine who has the authority to approve this request?
The team working on a project encountered and resolved a technical issue, allowing the project to continue. The project manager has been warned that the same issue will probably arise in similar projects.
What should the project manager do first when responding to this warning?
The project manager schedules an iteration review and learns that key stakeholders disapprove of the development of a feature.
What should the project manager do first to address the issue?
Before the next iteration begins, the project team must meet an unexpected challenge that threatens to delay the current pace. The task in the next iteration cannot be completed because of this challenge. Another team within the project depends on the timely completion of the task in order to fulfill their work.
How should the project manager resolve the issue?
What is the schedule variance if PV = 4000, AC = 2000 and CPI = .75?
An agile project team has implemented design changes over several iterations. The data privacy officer is concerned because their team wasn’t involved in these decisions.
How should the project manager address these concerns?
A project manager struggles to keep a technical system implementation on track after losing a critical team member two months ago. The project has missed multiple milestones and is now in critical status.
What should the project manager have done to prevent this situation?
After comparing actual results to the performance measurement baseline, the project manager discovers that the project’s work and cost performance measures are better than expected. The project manager doubts that these favorable variances can continue until the end of the project.
What should the project manager do?
A 10-month site development project started on 1 January. The current performance is as follows:
* The schedule performance index (SPI) is 1.2.
* 80% of the work is complete.
* The planned value of the project is US$100,000.
* The cost performance index (CPI) is 1.1.
Which option identifies the current time and actual cost (AC)?
A project manager is leading a development project for an external customer in another country. The project manager’s company is required to comply with certain regulations, and the project manager’s project has been selected for an audit. The customer does not think the audit is necessary and has asked the project manager not to disturb the project team.
What should the project manager do?
The success of an ongoing agile project is measured as follows: (table)
Sprint | Stories Planned | Stories Completed | Planned Value | Earned Value |
1 | 15 | 10 | 450K | 300K |
2 | 20 | 18 | 600K | 540K |
3 | 20 | 25 | 800K | 1000K |
4 | 22 | 25 | 1100K | 1250K |
Two weeks Sprint – stories planned – stories completed – plan value – earned value
What two conclusions can be drawn from these figures?
(Choose two)
The project is seven months into execution. The project manager determines that the cost performance index CPI is .80.
According to a trend analysis, the CPI has a downward trend.
What should the project manager do next?
A new law is expected within the next six months that will affect the business product line. The following product is launching and should be completed within three months. Unfortunately, the new product will not meet the proposed law’s requirements.
How should the project manager respond to this potential problem?
A project that should have been 70% complete by now but is currently only 55% complete. The total budget is USD $210,000, and the actual spent today is USD $162,000.
What is this project’s schedule performance index (SPI) and the cost performance index (CPI)?
(Try to estimate and eliminate answers before doing the math)
A project manager receives complaints from a project sponsor because of the delay in developing a prototype.
The project manager consulted with the resource management plan and discovered that the delay was due to a lack of knowledge in a specific skill that was needed by the cross-functional project team.
How can the project manager perform this task better in the future?
An efficient, agile team in a large corporation generated ideas and added innovative features to the backlog. After the additional features are evaluated and completed, the portfolio owner rejects all of them.
What is the most likely reason the situation happened?
How might performance metrics be distorted?
A project manager is working with a new team on an agile project. The team is regularly missing milestones and are unable to meet the pace of the sprints.
How should the project manager proceed?
During a team meeting, team members discussed a project’s external dependencies and asked the project manager for advice. What should the project manager ask the team to do?
A project is showing a negative schedule variance. The project manager sees that one team is causing the delays.
What should the project manager do?
A project team has intermittent problems with transportation to a remote site. Work is scheduled for an 18-month interval that includes only one rainy season to minimize the impact. However, now the site has been overrun by invasive weeds. Specialists are needed to inspect the site, but the timeline has been impacted and the project is in danger of being derailed.
How should the project team handle this situation?
Multiple stakeholders express dissatisfaction with a project deliverable.
What should the project manager do next?
The customer indicates they would like to add functionality to a product in development. Although this request was made during the execution stage of the project, the project manager determined that the cost for the additional cost would be small. The additional functionality, if successful, would increase the opportunity for profit.
What should the project manager do next?
Ongoing agile project is measured as follows:
Sprint | Stories Planned | Stories Completed | Planned Value | Earned Value |
1 | 15 | 10 | 450K | 300K |
2 | 20 | 18 | 600K | 540K |
3 | 20 | 25 | 800K | 1000K |
4 | 22 | 25 | 1100K | 1250K |
Total | 77 | 78 | 2950K | 3090K |
According to the table, which two of the following are the project metrics?
(Choose two)
The project team has been efficiently delivering results. The product upgrade they are working on must be released in three months, or else the competitor’s new product will make theirs obsolete. Citing that reason, the product owner suddenly requests a feature revision. However, no one on the project team is capable of doing the work. The project sponsor is willing to extend the budget but cannot extend the schedule.
What should the project manager do?
A steering committee has replaced the project’s single sponsor due to a significant increase in the project size.
What should the project manager how should the project manager approach this change?
Several items remain blocked in a Kanban column despite the team’s effort to address that. The retrospective reveals that the impediments can be traced back to a particular department head. Previously, the project manager has tried to educate the stakeholders, but they still show resistance.
What should the project manager do next?
A project manager identifies three critical risks with the probability of high impact on the schedule and budget of the project. This project is producing critical deliverables for the company.
The team member meets to devise a solution for the risk and decide that three specific resources will be required to address the risk. However, these resources are already committed to a separate project, which a different project manager manages.
Which party should the project manager work with first to find a solution?
How might a project manager in a predictive environment choose to tailor the team’s approach to address too much work in progress and high rates of scrap (waste)?
At the end of an iteration, a team member tells the project manager that a planned task is unfinished because of an issue that appeared days ago but could not be resolved. Why should the project manager discuss the issue during the retrospective to prevent this type of situation in the future?
A project manager learns that a few stakeholders disagree regarding the results of one project deliverable.
What is the next step the project manager should take?
A project manager identifies a risk during the implementation phase of a project that was not anticipated during planning. How would facilitating a brainstorming session allow the project manager to mitigate the risk while keeping the project on schedule?
A competitor company has accused a project of an intellectual property (IP) violation, specifically use without permission. In a letter addressed to the CEO, the competitor company’s lawyer demands surrender of the prototypes and all collateral containing the IP. The project sponsor encourages the project manager to keep working and deliver the product as planned.
What should the project manager do?
During a high-risk project, several risks have been materialized and responses have been implemented, However, the project still appears to be in trouble. The project manager is concerned that the risk management rules are not being carried out as specified.
What should the project manager do to identify the weaknesses of the risk management process?
A project is 50% completed.
An essential project team member requests two months’ leave for personal matters.
What should the project manager do first?
A project manager works with the customer who repeatedly submits requests for new requirements for existing software products.
The project manager has already provided the stakeholders with the completed scope definition for the product’s next version release.
Which step is appropriate for the project manager to take next?
The trend shows that stories are incomplete, which becomes apparent at the end of the iterations. Several team members worked on the stories, and no blockers were identified.
How can the agile team resolve the situation?
The project has a quality management plan in place.
This plan states the project deliverables must be reviewed for quality at least five business days before the deadline.
What should the project manager do for deliverables that fail the quality requirement?
A contractor sent an email request for urgent payment of their last invoice on a project going through a long execution phase stage with multiple contractors.
How should the project manager respond to the contractor’s request?
During an iteration, the project team working in France encounters problems that may cause a delay in the completion of a specific task. Teams in Spain need the task to be completed to meet their schedules. These teams work together virtually.
What can the project manager do to resolve the problem?
A project management organization needs to assess the performance of two project teams. Both projects have the same scope of work, but Team 1 works virtually and has calculated 100 story points, while Team 2 works in the office and has calculated 80 story points.
Which team has the better performance?
Two stakeholders informed the project manager that the status of a critical project phase was not communicated to them. Although the project phase is in these stakeholders’ areas of interest, the stakeholders have only recently been identified. What should the project manager do first?
While reviewing the quality of deliverables with the team, the project manager determined that several quality issues could have been avoided by using a checklist. The project manager implements a checklist to ensure that future deliverables align with the project management plan.
What did the project manager do in this situation?
Which type of key performance indicators (KPIs) provide early warning signs of potential problems?
An external provider is late with the delivery of a finished item. As a measure of goodwill, and to maintain the project’s schedule, the provider offers to bear the cost of renting a temporary system.
Since no schedule slippage will occur, what should the project manager do next?
An empowered agile team showed impressive progress in the first four iterations, but now the product owner has noticed low output in the latest five iterations without any apparent reason.
What could be the cause of this situation?
The product owner repeatedly complains, saying that a function developed by the development team does not seem to align with the original design.
What will help to solve this issue?
Significant variations have occurred with the project scope and schedule after six iterations. These are due to the customer’s technology regulations and security policies, which are regularly reviewed. The project manager suggests taking innovative approaches to the next iteration to avoid possible delays.
What should the project manager do first?
Most of an agile team’s members are away for a month, but the project must make progress. The project manager outsources the work to overseas contractors to work remotely on the stories. In their first sprint, the overseas team did not understand specific usability requirements but still managed to complete five previously blocked stories because the original team could not handle the algorithmic complexity of the work.
What should the project manager do in this situation to make progress on the project?
An R&D unit executive who is a project stakeholder occasionally visits the agile team’s work area to give instructions about urgent feature work. The team begins work. During the sprint reviews, the product owner became upset that the team worked on the requested features.
How should the project manager address the problem?
A project manager is also a business manager in a highly regulated industry. The project sponsor, a high-level executive, has asked for changes that disregard legal requirements.
What should be the first step in the project manager’s response?
What does it mean that deliverables have been verified?
The stakeholders and project team working on an agile project meet with the project manager at the end of an iteration. The project manager learns that the schedule is slipping, although all work was planned to meet the high-level objectives outlined in the project scope.
What should the project manager have done to keep the project on track?
A project manager learns that the project team will miss a milestone because team member A has not completed the task requirements needed by team member B. When meeting with team member A, what should the project manager do?
A project is entering the user acceptance testing phase. After several business end users raised questions and concerns, the project manager discovered that critical business requirements were omitted from the business requirements analysis.
What should the project manager do to resolve this issue?
A skincare company reports growing customer complaints about underweight products.
The project manager needs to determine if a change on the production line is needed.
Which tool or technique can the project manager use for this task?
A project has the following characteristics:
Which action should the project manager take?
An agile team needs help to solve a blocking issue with packaging design. Eventually, they find a solution, requiring a different product format.
What should the team do before further developing the solution?
A planned task in a sprint was nearly completed because of an issue that appeared three days prior but was not resolved. The team revealed it in the next daily standup meeting, but the project manager wants to prevent this type of situation.
Which of the following should the project manager do?
A project manager must ensure that all data security requirements are covered during a data warehouse development project’s execution stage. Each database created during different project phases must have a specific data security policy to comply with governmental data security laws.
How should the project manager plan to meet these requirements?
The project team collected sensitive client data during the initial stages of a project to help develop the project management plan. The team is now working on deliverables for the project when the compliance manager discovers a data breach and alerts the team to a compliance issue.
What document should the project manager review first?
What is an acceptable cause for revising a project’s baselines?
The director of security compliance is upset because the compliance team has not been informed about the product design decisions taken by the agile team members over the past five iterations.
What should the project manager do to start correcting the situation?
A project manager leads a project with an aggressive timeline that requires fast time to market because a competitor is working on a similar product. The project team cannot meet the go-live date, and no other internal resources can assist.
How should the project manager mitigate this risk?
A significant risk to a project is identified, and the risk management plan is executed. Upon completion of the approved actions, what should the project manager do?
A project manager recognizes that certain components must be imported to meet the project’s requirements. However, due to the potential impact of an unfavorable exchange rate, the project manager decides that incurring a loss is not justifiable and chooses not to take any action to mitigate it.
Which risk response strategy did the project manager employ?
The company has hired a new architectural excellence board to promote new programming paradigms. The agile team continues to work on new and existing software products.
How should the project manager deal with this new development?
The agile team will take over from another supplier to maintain a client’s website. The team notices that recent browser changes imply that most of the website’s existing content would now require users to install a plug-in.
How should the agile team move forward?
The agile teams surpasses the planned number of stories in the last three agile iterations.
How can the project manager be sure all the work performed is complete?
The pandemic has caused delays, making it exceedingly difficult to launch a new product on time. Television ads for launch dates have already been purchased, so the CEO has asked the project manager to find a way to launch the product even if some minor features are not included.
What would be the most effective step toward a successful and timely product launch?
Certain key stakeholders are dissatisfied with the development of the project’s key feature. They express their dissatisfaction during an iteration review meeting.
What should the project manager do first to resolve this issue?
After completing a project, the team meets to conduct a lessons-learned session. During this meeting, the team saw that all deliverables were completed within the defined parameters. However, during the testing, a large number of errors were identified.
What should the project manager have done in this situation?
A project manager is responsible for a new agile project that is global in nature. After a few sprints have been completed, the quality assurance team, based in a different country from the PM, has generated a long defect list. The PM is certain that these issues are not related to project quality, but are from language misinterpretation.
What should the project manager do to address these issues?
A project that should have been 75 percent complete by now is only 65 percent complete. The total project budget is US$200,000, and the actual cost of work performed is US$110,000.
What can be determined from this information?
A vendor informs a project manager that the equipment can be delivered earlier than anticipated. The project manager recognizes that this is an opportunity to complete the project ahead of schedule.
What should the project manager do next?
A project manager identifies new risks that might affect the completion of critical tasks. The project manager needs to present these new risks to project stakeholders in the monthly status report.
In addition to the risk report, which document should the project manager reference when preparing the status report?
A merger of two companies combines an agile software project and a predictive electronics project into a hybrid project. Two months later, requirements changed in both tracks, but neither had a complete picture of the status or importance of the requirements.
How can the project manager best resolve the problem?
The marketing director is displeased that the agile innovation team is producing too many novelty products with too little business value.
Which two approaches should the project manager take to correct the team’s approach?
(Choose two)
Several unforeseen impediments suddenly appear on the Kanban board for a hybrid project. Each team member has reported one or more different problems relating to a regulatory specification issued by the predictive track.
Which parameter is likely to be highest in the risk assessment?
Some customers and users have not completed the required training. The project manager must consider the risk it poses to project’s timely completion. End-user training is a required project deliverable.
Which action should the project manager perform?
The project sponsor asked the project manager to change production materials because these materials could cause health problems for the consumers.
Which step should the project manager take?
A team misunderstood one product functionality documented in an earlier project stage. During the current iteration, the functionality has not yet been developed, but a business representative has mentioned the deficiency.
How should the project manager proceed?
What should you do to reduce risk exposure when previously approved risk responses have not been implemented?
A key stakeholder has submitted several requests for new functions for a product under development. The project manager just completed the scope definition for the product’s next version release and communicated the scope statement to all stakeholders.
What should the project manager do next?
A project team received training on the technology involved with a project deliverable. Several team members have been replaced in nine months of working on the project. Productivity has slowed because new team members are unfamiliar with the technology, and the project schedule is at risk of being delayed.
What should the project manager do?
A project manager is leading a project to develop a new system for a government agency using a predictive approach. The project’s governance framework is designed to ensure that the system meets the needs of the stakeholders and complies with all applicable regulations. The project manager receives an approved change request for a project’s governance framework.
What should the project manager do to implement this change?
A project is nearing completion when the project manager learns that a change in market regulations may impact the project. What should the project manager do?
Before preparing a monthly project status report, project team brings three risks to the project manager’s attention.
The project manager wants to reference additional information before presenting this as new risk information.
Where can the project manager look to evaluate these risks?
A project manager for a construction firm meets with stakeholders. All stakeholders agree on a 20-month lifecycle for a project. After work has begun, the project manager learns that stakeholders would like the project to be completed within 16 months at most.
Which step should the project manager take?
While reviewing the issue log, the project manager notices that tasks assigned to two team members are behind schedule.
What should the project manager do?
A project is started with an approved scope.
As the team implements the project design, a team member states that the product will not meet approved requirements in certain situations. Correcting the issue increases scope and cost, and the project will also miss the deadline.
The project sponsor does not have additional funding to support the project.
What should the project manager do first?
An organizational change program has met with internal resistance, a previously identified risk. A logistics manager is particularly affected, due to the reduction of the team size and the rate of change driven by agile planning of the predictive implementation. The product manager or supervisor formally requests the change program to delay the team’s implementation.
What should the project manager do next in response to this request?
A project manager for a virtual team reviews progress during the third iteration of project product development. Still, the team dashboard that shows progress on work is faulty and is not showing updates.
What action should the project manager take?
Since the beginning of the project, the product owner has kept asking during ceremonies about the budget spent on each iteration. The product owner seems much more interested in the cost than in the product itself.
What should the project manager have done earlier to change the product owner’s behavior?
A project team received training on the technology involved with a project deliverable. Several team members have been replaced in nine months of working on the project. Productivity has slowed because new team members are unfamiliar with the technology, and the project schedule is at risk of being delayed.
What should the project manager do?
A supplier for a regulatory project is responsible for making the component changes. The supplier is unlikely to meet the project schedule. Based on the risk response plan, the project manager secured stakeholder approval to use paper forms until the component changes go live. It is still possible, however, that the paper form changes may not be ready in time.
Which risk type is the project manager facing in this situation?
A new project manager resumes a project in its execution phase. During a project status meeting, a team member reports an issue shared by a stakeholder.
What should the new project manager do first?
An innovative product fails to satisfy targeted consumers despite significant investments in quality control and marketing campaigns.
Which agile practice will prevent future failures of this nature?
A project manager is working on a software development project.
The completed scope definition for the project’s next version release has already been provided to stakeholders; however, two customers are repeatedly submitting new feature requests.
What should the project manager do next?
Two months into a three-year mobile telecom rollout, the project manager discovers that approximately 15% of the equipment is prohibited for delivery because of an embargo. The procurement contract does not cover the embargo case, but the company could, in court, incur several penalties for incomplete delivery.
What is the appropriate solution for this situation?
The agile team is tasked with building a version of the smartphone shopping application suitable for older people. Marketing has not found any volunteer test users fitting the profile.
Which action would be the most effective ensuring the best product value is delivered?
While monitoring the progress of the agile team, the project manager notices that an experienced member’s output is much lower compared with that of junior team members. This is a surprise, as the expert works diligently on the most complex task and always produces defect-free results.
Which is the most likely explanation for the developer’s low output?
A hybrid pharmaceutical project adds new activities for the team to run machine learning (ML) processing of medical scans. An agile team of doctors uses the output from the ML analysis to determine next steps in a patient case. The project manager has updated the scope statement and schedule.
In which three of the documents should the project manager record this new process? (Choose three)
What should you do when you observe the development team spending a significant amount of time responding to operational issues and, upon review of the project schedule, determine their activities are behind schedule?
A project manager is working on an agile project. The project has 100 user stories broken down into ten iterations. Each user story is worth US$100. The actual expenditure is US$4,500, and 50 user stories were delivered after five iterations.
Which statement is accurate?
A project manager is leading a project to deliver a new product to the market. The project sponsor has asked for a broadened scope and to provide a “scaled-up version” of the final product.
What should the project manager do?
A supplier reports being over capacity, which may delay their delivery. What should the project manager update?
The end customer rejects a deliverable that does not meet the agreed-upon quality specifications and is rejected by the end customer. After investigation, the project team finds a fault with the vendor-provided parts, which caused the issue.
The vendor says that they cannot correct the situation.
What should the project manager review before deciding on the next steps?
A startup company needs to quickly expand its product portfolio to meet market demand. Recently, staff members have worked on two or three agile teams, each dedicated to a different product line. Output is diminishing, and defect rates are rising in all teams.
In which two ways can the project manager help the agile teams improve their work?
(Choose two)
A project manager implemented an approved change to manage risk. Three months after the implemented change, the project manager learned that the change did not produce the desired result, instead, it produced negative consequences.
How should the project manager avoid this problem on future projects?
A retiring project manager hands materials to a new project manager. The project appears to be running smoothly until a critical component fails during testing.
What is the appropriate first step when responding to this issue?
A project manager develops the project management plan and schedule based on an agreed-upon project lifecycle of 16 months. Later, due to changing business requirements, the project sponsor requested completion within nine months.
How should the project manager respond to this proposed change?
A project’s workflow is increasing significantly, and the resource level is insufficient. In response, management outsources some primary tasks to keep the project on schedule.
What should the project manager do in this scenario?
A project has the following characteristics:
Which statement about the current status of the project is true?
What does a horizontal trend line on a scatter chart represent?
A project manager is assigned to join a mega-industrial project already underway. The latest performance indices are CPI=0.42 and SPI=0.20. This project is:
The supplier of a tool for a manufacturing project informs the project manager that delivery will be late. The project manager orders the tool from another supplier. After the tool from the second supplier arrives, the original supplier delivers the tool and submits an invoice according to the procurement agreement.
What should the project manager do next?
A project’s outcome is highly sensitive to and dependent upon financial market activity. Therefore, the company’s financial advisor delivers daily exchange-rate forecasts. The project’s budget was planned using a conservative scenario with high exchange-rate variations. The project manager wants to review this budget to update the probability and impact of a possible new scenario using current financial conditions.
To what should the project manager refer?
Steve is looking at his project budget and notices that the cost and staffing levels are high. At which point in the project will this generally be?