Project team members spend a lot of time helping maintenance and operations staff for the recently commissioned project component.
The project manager must validate that the component was signed off and ownership transferred.
Which three documents should the project manager use for this decision?
A project manager has completed the following steps:
Which next step should the project manager take?
After the project ends, the project manager and project team members are still being asked to do the following:
The project manager wants to ensure the product or service developed by the team now has operational support.
What should the project manager do?
You are nearing completion of the project and have already been assigned to manage another new project. You are nearing completion of the project and have already been assigned to manage another project that will start next week. While you are excited to start work on the new project scope, you understand the deliverables of the current project must be turned over to the customer.
What should you do next?
A software development project is nearing completion. The project team is responsible for determining if the product is ready for delivery.
Which two action should the team members take? (Choose two)
A project manager needs to complete a project formally, but a supplier says an invoice has been paid twice. The project manager knows the invoice was approved but cannot find evidence of a duplicate payment. The project manager must close out this project to start a new one.
What should the project manager do?
The project sponsors for a multinational project have implemented a process that generates emails and reports at the end of each phase. The goal is to ensure the project remains unified across the company, and the company plans to use the process as a model for future, similar projects.
What should the project manager do?
Upon completion of a long-term contract, the project manager confirms with the release manager that all planned features are functioning properly, as verified by the quality assurance team. The project manager informs the customer and project stakeholders and obtains the approval to close the project. The project is now closed.
What should the project manager do next to ensure that the knowledge gained during this project remains available for future reference?
A large project involving functional groups in four countries is nearing completion. The project manager is meeting with the functional managers to prepare closeout documents.
Why should the project sponsor sign off on the acceptance of project deliverables?
A project manager is concerned that team members spend too much time assisting operations and maintenance staff with a recently completed and delivered project component. The project manager referred to the organizational process assets document to validate that the component had been signed off and ownership had been transferred.
To which additional documents should the project manager refer?
A medical equipment vendor is running a hybrid project that includes custom software development by the agile team. The team’s progress is good, but slow customer approval causes unnecessary delays. The customer insists that the approval can only be given after repeating all the test cases in the target environment.
How can the project manager accelerate the approvals and build customer trust simultaneously?
A customer has informed the project manager that they do not accept the project deliverables. What should the project manager do to gain approval?
Review the following steps:
What is step three?
After weeks of dealing with conflicts, compromising, and achieving the project goal, team members focus on documenting the lessons learned to be shared with stakeholders, sponsors, and future project teams.
What phase are they most likely in?
The legal team informs the product owner that another company owns a patent for the innovation used in the agile team’s product, which is now 75% complete.
What should the product owner do to determine the appropriate way forward?
A project manager is formally closing a project that has been completed.
Why should the project manager document final project activities?
A project is completed, and the project manager and project team members are being asked to do the following:
The project manager needs to ensure that the product developed by the project now has operational support.
What should the project manager do?
A project team is working on a software development project. As the project nears completion, the team must determine if the product is ready for delivery.
Which two actions should the team take? (Choose 2)
A large project includes functional groups in four countries, a steering committee, and a project sponsor. The project manager must prepare the closeout documents as a project approaches completion.
How should the project manager obtain the appropriate sign-off on accepting project deliverables?
Review the following project characteristics:
What is the first action the project manager should take?
How can a project manager gain stakeholder approval if the stakeholder believes a project’s deliverables were not achieved?
A customer is not satisfied with the delivered product, saying it was different from what they expected. The project manager is surprised because the agile development team delivered the product several iterations early.
What is one way that the product manager and the project manager could have avoided this result?